Our Projects
  • CURRENT
  • COMPLETED
Architect/Consultant

 

Description of Project

Provision of Phase 1 Site Preparation Work For the Proposed Refinery And Petrochemicals Integrated Development (RAPID) Project - Package 1

Contract Sum

5.1 mil

Date Of Start

15th Oct 2012

Date Of Completion

31st Dec 2013

Gallery

Architect or Consultant

Mitsubishi Heavy Industries Ltd.

Description of Project

Civil and foundation works for Shuqaiq II Independent Water & Power Project At Kingdom Of Saudi Arabia.

Contract Sum

68.5 mil

Date of Start

15th Feb. 2008

Date of Completion

30th Dec. 2009

Architect/Consultant

Eastern Steel Sdn Bhd.

Description of Project

Earthwork For The Proposed Integrated Iron And Mild Steel Phase 1 At Teluk Kalung, Kemaman Terengganu For Messrs Eastern Steel Sdn. Bhd.

Contract Sum

3.0 mil

Date Of Start

May 2012

Date Of Completion

Octo 2012